Implementation tracker
Next steps
- Confirm the timeline for lower-environment installation.
- Schedule the install review session.
- Define the scoped list of reports to build in Pendo.
Project phases (5)
✓
Schedule Install Review
Done
✓
Schedule Recurring Project Sync
Done
Add Necessary Users to Subscription In progress
5 Oct – 16 Oct
✓
Complete Kickoff Call
Done
Scoped reports list to be created In progress
16 Oct
Update plan based on scoped reports list NEXT
19 Oct – 23 Oct
✓
Plan Installation Approach via Architecture Review
Done
Install Complete - Lower Environment NEXT
9 Oct – 16 Oct
Review and Confirm Install via Install Review Session
9 Oct – 16 Oct
Install Complete - Production Environment - App 1
22 Oct – 30 Oct
Consultation meetings NEXT
8 Oct – 20 Nov
Data Validation
13 Nov – 27 Nov
Knowledge Transfer
27 Nov – 10 Dec
Tagging and Segments Enablement NEXT
14 Oct – 23 Oct
Analytics Enablement
16 Oct – 23 Oct
Office Hours for building reports NEXT
21 Oct – 27 Nov
All Scoped reports were built
27 Nov – 30 Nov